What Does Warranty Actually Mean on a BESS Project?

· 8 min read · Guide

BESS warranty — DLP vs product warranty

Ask five people on a utility-scale BESS project what “warranty” means, and you’ll get five different answers. The EPC contractor is thinking about their defects liability obligation. The equipment manufacturer is thinking about their limited product warranty. The asset owner assumes someone is responsible for fixing whatever goes wrong. The insurance provider is trying to figure out what falls outside their policy. The developer may mean something different again depending on which contract they’re looking at.

None of these people are wrong. They’re just talking about different contractual mechanisms — using the same word. And that misalignment stays unnoticed right up until the moment it matters most: when a defect appears, the plant is unavailable, and nobody agrees on who is responsible, who should pay to resolve, how fast it needs to happen, or which terms and conditions actually apply.

This article breaks down what “warranty” actually means on a utility-scale BESS project.

Warranty and Guarantee Are Not the Same Thing

Before getting into the warranty mechanisms, there’s a distinction that gets blurred constantly — sometimes even within the same contract document. Warranty and guarantee are not interchangeable terms in a BESS project, even though they’re routinely treated as if they are.

Warranty refers to an obligation — a set of terms and conditions governing how defects in hardware, software, or design will be handled after the equipment has been installed and is in operation. If a piece of equipment fails despite being used within the agreed operating conditions, that’s typically a warranty case. If that same equipment fails because it was operated outside the agreed conditions — wrong ambient temperature range, exceeded cycle count, improper maintenance — it’s typically not.

Performance guarantees are a separate category entirely. On a utility-scale BESS project, the most common performance guarantees are:

  • Energy capacity guarantee
  • Round-trip efficiency (RTE) guarantee
  • Availability guarantee

These are contractual performance commitments. They come with their own terms and conditions, their own test procedures, and their own liquidated damages if the thresholds aren’t met. They are not warranty. They don’t follow warranty logic. Mixing the two up during contract negotiations creates problems that surface months or years later.

It’s common to see EPC contracts and developer requirements where “warranty” and “guarantee” are used interchangeably throughout the document — or where everything is called a “guarantee,” even when it’s clearly a warranty topic. This leads to friction during contract negotiations that end up taking longer and producing weaker outcomes than they need to.

Warranty vs. Performance Guarantee Warranty covers defects in equipment and workmanship. Performance guarantees are separate contractual commitments with their own test procedures and liquidated damages.

The Two Warranty Mechanisms

This is where most stakeholders get confused, and where clarity matters most. On a utility-scale BESS project, there are typically two distinct warranty mechanisms in play. They look similar from a distance, but they are fundamentally different in scope, ownership, and how they work in practice.

1. Limited Product Warranty

The Limited Product Warranty is provided by an equipment manufacturer for their specific product, based on their own terms and conditions. It’s a legal instrument tied to the purchase or sales agreement for that equipment.

On a utility-scale BESS project, there isn’t one Limited Product Warranty — there are several. Each major piece of equipment comes with its own:

  • The DC block has its own Limited Product Warranty from the DC block equipment manufacturer
  • The power conversion system has its own from the PCS provider
  • The transformer has its own
  • The power plant controller may have its own
  • Additional electrical infrastructure — switchgear, cabling systems, protection equipment — may each come with separate warranty terms

A Limited Product Warranty typically specifies what the equipment manufacturer warrants: that the equipment shall be free from defects in material, workmanship, and sometimes design, for a defined period of time, provided the equipment is operated according to specified conditions. If a defect falls within the warranty scope, the document should set out the remedies — typically repair or replacement of the defective component. In some cases, where repair or replacement isn’t practical, the warranty may include liquidated damages provisions as an alternative remedy.

The critical point: whoever holds the sales contract or purchase agreement for that equipment owns the right to those warranty terms and conditions. This becomes very important depending on how the project is structured — more on that below.

2. Defects Liability Period (DLP)

The Defects Liability Period is a contractual obligation embedded in an EPC contract, between the EPC contractor and the buyer — typically the developer or asset owner/investor. It is not a Limited Product Warranty. It is a contract clause that makes the EPC contractor responsible for rectifying any defects in their works during a defined period after handover.

The terminology for this varies by region and contract form. You may see it called the defects notification period, or in some languages and jurisdictions, a guarantee period or other regional equivalent. The phrase varies, but the core concept is typically consistent.

What the DLP covers is fundamentally broader than any single Limited Product Warranty. It applies to the EPC contractor’s entire scope of delivery:

  • Workmanship and design
  • Equipment (DC block, PCS, medium voltage, power plant controls, etc.)
  • System integration
  • Balance of plant (civil works, electrical infrastructure, installation)

If something is defective during the DLP — regardless of whether the root cause is the EPC contractor’s own work, a subcontractor’s work, or a piece of equipment procured by the EPC contractor from an equipment manufacturer — the EPC contractor is the responsible party. The duration is typically one to two years from handover, sometimes up to five, depending on what has been negotiated.

Why This Distinction Matters: The Single Point of Contact

This is the point that many stakeholders miss, and it’s arguably the most important practical consequence of the DLP.

During the Defects Liability Period, the asset owner or buyer has one point of contact: the EPC contractor. It doesn’t matter whether the root cause of a defect is a wiring issue from the EPC contractor’s own installation team, a malfunctioning battery module from the DC block equipment manufacturer, a software bug in the BMS, or a failed PCBA in the power conversion system. During the DLP, the EPC contractor owns that problem. They are the party contractually obligated to investigate, manage, and rectify the defect according to the agreed terms and conditions.

The EPC contractor, in turn, will need to deal with the relevant equipment manufacturers under their own purchase agreements and Limited Product Warranties. But that’s the EPC contractor’s problem to manage — not the buyer’s. The buyer doesn’t need to chase five different equipment manufacturers across five different warranty documents. They go to the EPC contractor.

This single point of contact is one of the key reasons organisations choose an EPC contract structure. It simplifies warranty management during the most critical early operational years of the plant.

Warranty Mechanisms Under an EPC Contract Under an EPC contract, the buyer claims against the EPC contractor during the DLP. The EPC contractor manages equipment manufacturer warranties downstream.

What Changes in a Developer-Led Structure

Not every BESS project uses an EPC contract. In a developer-led approach — sometimes called direct procurement or split contract — the developer contracts directly with equipment manufacturers and bears responsibility for the system integration themselves, often using separate subcontractors for engineering and balance of plant (BoP).

In this structure, the DLP as described above doesn’t exist in the same way, because there is no single EPC contractor carrying overall responsibility. Instead, the developer holds multiple purchase agreements directly with equipment manufacturers, each with their own Limited Product Warranty and/or specific purchase agreement terms.

The single point of contact disappears. The developer is now the party responsible for negotiating separate terms and conditions with each equipment manufacturer, and for managing any warranty claims that arise — coordinating between multiple parties, each with their own response times, remedy procedures, and exclusions.

This isn’t inherently better or worse — it’s a different risk profile with different management requirements. But anyone involved in a developer-led project needs to understand that the warranty landscape looks fundamentally different from an EPC-delivered project.

What Happens When the DLP Expires

When the Defects Liability Period ends, the EPC contractor’s obligations under the DLP expire. The asset owner is now fully responsible for the BESS plant.

In practice, this transition is rarely as abrupt as it sounds. Most asset owners will have an operations and maintenance arrangement in place — either performing service themselves or engaging a service provider, which in many cases is the EPC contractor itself. These long-term service agreements often include terms that go beyond what the DLP covered in terms of responsiveness: faster response times, local storage of spare parts, remote monitoring and access for preventive and predictive maintenance. The service provider may also take on the coordination of any remaining equipment manufacturer warranty claims that are still active after the DLP has ended, since the Limited Product Warranties from equipment manufacturers often run longer than the DLP itself.

The key thing to understand is that the DLP expiring doesn’t mean all warranty coverage disappears. The Limited Product Warranties from each equipment manufacturer continue according to their own terms and durations. What disappears is the EPC contractor as the single point of contact and the party obligated to rectify defects across the full scope of works.

Get the Terminology Right

Aligning on the terminology from the beginning — during contract drafting, procurement, negotiations, and project management from execution to operations and maintenance — is the best way to avoid misunderstanding and friction between stakeholders. Two warranty mechanisms, properly defined and separated from performance guarantees, with informed stakeholders, is something all parties will benefit from.


learnBESS covers the full BESS project lifecycle — from procurement and factory acceptance through commissioning and operations — in our BESS Fundamentals course.